Heatham House

Works comprised of the following:

  • Set up the site, welfare and storage compound, install secure timber hoarding, painted with display boards, site safety signage, and temporary lighting and information boards.
  • Asbestos Works.
  • Install tree protection, secure timber protection casing of the street front metal railings, walls and piers.
  • Enabling alterations to services to allow main building to function
  • Demolition works.
  • Temporary protection of Main Building.
  • Construction of extension.
  • Reconfiguration and refurbishment of existing building including external cladding and sound proofing.
  • External hard and soft landscaping.